What is a prime cost sum?

A prime cost sum, often written PC sum, is an allowance in a building contract for a specific item the client will choose later, such as tiles, tapware or appliances. It covers the cost of supplying the item. The contract price is adjusted up or down once the real cost is known.

PC items are things whose scope is clear but whose price is not, because the client has not yet picked a product. The allowance is the builder's estimate of what the item will cost to supply. Installation, and the builder's margin on the item, are normally dealt with separately in the contract, and it is worth checking the wording on how they are treated.

When the client chooses something dearer than the allowance, the difference is added to the price. When they choose something cheaper, the difference should come off. Either way it should be documented as an adjustment rather than left to the final account.

The usual source of disputes is an allowance that was set too low to be realistic. A PC sum for a bathroom tile range that no one would actually choose looks cheap on the quote and becomes a large adjustment later. Clients should be given a realistic allowance and a deadline for making their selection, so the choice does not delay the build.

A prime cost sum is not the same as a provisional sum. A PC sum is for supplying an item the client chooses. A provisional sum is for work whose scope cannot be fully described at the time of the contract.