What is an RFI in construction?

An RFI, or request for information, is a formal written question raised during a building project to clarify the plans, specifications or site conditions, such as a conflict between drawings. It is sent to the person who can answer, with a date, and the answer is recorded.

RFIs are raised by builders and subcontractors when something cannot be built as documented. Typical triggers are a conflict between the architectural and structural drawings, a missing dimension, a product that is no longer available, or a site condition that was not shown.

A good RFI is specific. It states the question, references the drawing or specification, includes a photo or markup if that helps, says who should answer, and sets the date by which a reply is needed to avoid delay. The answer should be written down, whether it comes by phone, email or meeting.

The paper trail is the point. If the answer changes the scope, cost or time, the RFI links directly to a variation. If it delays the work, the date the RFI was raised and the date it was answered support a claim for more time.

Unanswered or lost RFIs cause real cost. Work built on a verbal answer that nobody recorded is hard to defend when the client later disagrees. Keep each RFI numbered, with a status, so nothing stays open and unseen.