What is a site diary?

A site diary is the daily written record of what happened on a building site: who was there, what work was done, the weather, deliveries, visitors, instructions given, delays and incidents. Kept consistently and dated, it is a primary piece of evidence when there is a dispute about time or cost.

The entries that matter most are the ones that show why something took longer or cost more. Weather that stopped work, late deliveries, access problems, instructions from the client or architect, and the number of workers on site all tell the story of the job as it happened.

Disputes about extensions of time, delay costs and variations come down to evidence. A diary written on the day carries far more weight than a recollection written months later, and a gap in the record is hard to explain. Most commercial contracts require the builder to keep one, and many residential builders keep one even when not required.

A good entry is short, factual and specific. Record what happened and who said it, not opinions. Photos attached to the entry, with a date, make it stronger. If an instruction was given verbally, write it down that day and follow up in writing to the person who gave it.

Site diaries are also used in adjudication and in defect and insurance claims. Because they are so often relied on, make sure each entry is captured at the time and stored somewhere it cannot be lost, instead of in a notebook left in the ute.